When doing a MSP Import:

 

  •  MS Project files maintains dates even for a manually scheduled tasks. These dates are silently computed by MSP to indicate the dates as if the tasks are auto-scheduled.The MPP/XML file has these dates and are used Celoxis. The Schedule type of such tasks will be ‘Fixed Dates’.

 

When doing a MSP Export:

 

  • Fixed dates scheduled tasks will be exported as manually scheduled tasks.
  • Summary tasks will be exported as auto-scheduled tasks.

 