Resource Efficiency: Hours (Est)/Hours (Actual) as a percentage.
Let's look at an example: User - Peter who has Estimated hours as follows:
Apr | May | June |
---|---|---|
141 | 168 | 214 |
and Actual and Actual hours on planned activities as follows:
Apr | May | June |
---|---|---|
128 | 36 | 164 |
So, the Efficiency for sat April is (141/128)*100=110%. This shows that Peter is an efficient resource.
The efficiency is should always be measured on Tasks as Hours(Est) can only be entered against the tasks.
...