Attribute | Description | R/RW |
---|
Baseline |
%Comp | It indicates the % Complete |
of the task when it was baselined. |
So, even if your actual Finish date changes, the % Complete (Planned, Baseline) will always be calculated with respect to your Finish (Baseline).
R | |
Baseline Budget |
The budget of the task when the project/task was baselined. | R |
Baseline |
Cost | The estimated cost of the task when the project/task was baselined. | R |
Baseline |
Start | The start date of the task when the project/task was baselined. | R |
Baseline Start Variance |
The difference in days between the current Start date and the Start date when the project/task was baselined. | R | |
Baseline Finish |
The Finish date of the task when the project/task was baselined. | R | |
Baseline Finish Variance |
The difference in days between the current Finish date and the Finish date when the project/task was baselined. | R |
Baseline |
Effort | The Work in hours when the project/task was baselined. | R |
Baseline Effort Variance |
The difference between the current Work and the Work when the project/task was baselined. | R |