AttributeDescriptionR/RW
%Complete (Planned,
Baseline
)
%CompIt indicates the % Complete
(Planned)
of the task when it was baselined.
This is compared against the Finish (Baseline) date of the project.
So, even if your actual Finish date changes, the % Complete (Planned, Baseline) will always be calculated with respect to your Finish (Baseline).
 R
Baseline Budget
(Baseline)
The budget of the task when the project/task was baselined.R
Cost (Est,
Baseline
)
CostThe estimated cost of the task when the project/task was baselined.R
Start (
Baseline
)
StartThe start date of the task when the project/task was baselined.R
Baseline Start Variance
(Baseline)
The difference in days between the current Start date and the Start date when the project/task was baselined.R
Baseline Finish
(Baseline)
The Finish date of the task when the project/task was baselined.R
Baseline Finish Variance
(Baseline)
The difference in days between the current Finish date and the Finish date when the project/task was baselined.R
Work(
Baseline
)
EffortThe Work in hours when the project/task was baselined.R
Work
Baseline Effort Variance
(Baseline)
The difference between the current Work and the Work when the project/task was baselined.R