Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Lets look at an example: Peter's estimated utilization is as follows:

SeptOct
17%-

So, Peter's capacity for September is [(1-(17/100))*100] = 83%. For the remaining months, he is at full capacity, since he has no allocations.

...

Celoxis allows you to create as many Generic virtual Resources as you may wish. You can then see the allocation of hours against these Generic Resources on the Resource Load Chart in tandem with this reportĀ to decide how to schedule your tasks, whether they can be done in parallel, how many resources you would need to hire if you were to execute the tasks in parallel etc... Using these reports you canĀ define resource plans for proposed projects and work and analyze these plans against estimated resource capacity.

...