To add a Company Holiday:

  1. From the main menu, click on Image Removed and then Company Settings.
  2. Under Company sectionLogin with a user with administrator privileges and click on Administration option under the user profile.
  3. Under the Project Management section, click on Work Calendars.
  4. Navigate to the Exceptions tab.
  5. Click Add.
  6. From the For drop-down, select 'Everyone'.
  7. In the Summary box, type the name of your Holiday.
  8. From the Impacts Scheduling drop-down list select option - Non working.
  9. From the date picker select a date. You can create the event for a whole day or for a specific time (un-check the All Day checkbox and select the From and To dates). 
  10. Select the check box Time zone independent if you want the holiday to be on that specific date, regardless of the time zone.
  11. From the Repeat tab, select an appropriate option.
  12. Click Submit. The exception is added.