Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 6 Next »

As a project progresses, tasks often tend to get delayed. It is very useful for a Manager to be able to compute the finish date based on current progress. Celoxis allows you to compute a projected finish date for your tasks and project. This can be done by clicking on Recalculate Projections for a project.

The attributes which are calculated are:

  • Projected Start date of tasks.
  • Projected Finish date of a tasks.
  • Projected Finish date of a project.
  • RAG (schedule and budget) status of project.

To recalculate projections:

  1. Go to your Project.
  2. From the project's action drop-down, navigate to More
  3. Click Recalculate Projections.  

We automatically do these projections every day at a fixed time between 3 AM to 6 AM EST. The fixed time is algorithmically determined. Projections for Projects which are In Progress and have a plan start date before today and Deadline > today to -90d  is recalculated in this time.

  • No labels