This report helps the project manager align the projects in pipeline with the planned & actual resource utilizations utilization on planned activities to get insight into long-term capacity plans. This helps in informed data-driven decisions to ensure the most efficient use of the resources for ensuring project success.

Image Removed

This Estimated Utilization is computed as a percentage of estimated to available resource hours, while Actual Utilization is computed as a percentage of actual-approved to available resource hours. This report shows the Utilization of the resources in for the last quarter. Lets


Image Added 

 

 Lets take an example of Peter Parker.

Utilization (Est) = Hours (Est)/Hours (Available) as a percentage.
Assume, Peter works 8 hours a day from Monday to Friday.
 The 'Hours(Available)' column will show you this information. 

AprMayJune
176176168

Assume, Peter's Hours(Est) for last quarter is as follows. The Resource Load Chart or the 'Hours(Est)' column will show you this information. 

AprMayJune
131168214

Assume Peter's Hours(EstActual) on planned activities for last quarter is as follows. The 'Hours(Actual)' column will show you this information. e g

AprMayJune
36128581816444

Peter works 8 hours a day from Monday to Friday.  

So, the Estimated Utilization of Peter is as follows:
Utilization (Est) = Hours (Est)/Hours (Available) as a percentage.
For Apr (131/176)*100=74%.

AprMayJune
74%95%127%

 

Similarly, the Actual Utilization is as follows:
Utilization (Actual) = Hours (Actual)//Hours (Available) as a percentage.
For Apr (128/176)*100=73%

AprMayJune
17673%17633%16898%

So, the 

 Using this, the PM can see how a particular resource is utilized for a period and can plan smarter.

Note
iconfalse

If your users play multiple roles in different workspaces, then we recommend creating a custom field  (single select dropdown) on users - "Primary Department" and group on that field, instead of Workspace .