Estimated Utilization is computed as a percentage of estimated to available resource hours, while Actual Utilization is computed as a percentage of actual-approved to available resource hours. This report shows the Utilization of the resources for the last quarter.
Lets take an example of Peter Parker.
...
Assume Peter's Hours(Actual) on planned activities for last quarter is as follows. The 'Hours(Actual)' column will show you this information. e g
...
Using this, the PM can see how a particular resource is utilized for a period and can plan smarter.
Note | ||
---|---|---|
| ||
If your users play multiple roles in different workspaces, then we recommend creating a custom field (single select dropdown) on users - "Primary Department" and group on that field, instead of Workspace . |