Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

To create a work calendar :

  1. From the main menu, click on Image Removed and then Company Settings.
  2. Under Company sectionLogin with a user with administrator privileges and click on Administration option under the user profile.
  3. Under the Project Management section, click on Work Calendars.
  4. Under the Work Calendars tab, click on Add.
  5. Enter a suitable Name for the calendar.
  6. Select the appropriate Time Zone.
  7. Enter the Work Timings for the calendar. You need to enter time as 9:00 - 13:00, 14:00 - 18:00 with the 1 hour break. Do not enter anything for Off-days.
  8. Click on Save.

To edit a work calendar :

  1. From the main menu, click on Image Removed and then Company Settings.
  2. Under Company sectionclick  Login with a user with administrator privileges and click on Administration option under the user profile.
  3. Under the Project Management section, click on Work Calendars.
  4. Under the Work Calendars tabIn the new pop-up, besides the work calendar, click on the Edit icon (pencil-shaped).
  5. You can edit the Name, Time Zone, Work Timings.
  6. Click on Save.

To delete a work calendar :

  1. From the main menu, click on Image Removed and then Company Settings.
  2. Under Company sectionclick Login with a user with administrator privileges and click on Administration option under the user profile.
  3. Under the Project Management section, click on Work Calendars.
  4. Under the Work Calendars tabIn the new pop-up, besides the work calendar, click  click on the delete icon.
  5. A confirmation message is shown to confirm your deletion. Click on Yes if you want to delete the calendar.
     
Note
  • You can create multiple calendars with different work timings and timezones.
  • A user is associated with only one work calendar.
  • Deleting a work calendar will move the users under it to the Default work calendar.
  • Editing or Deleting a Work Calendar will reschedule all the incomplete tasks assigned to the resources based on the new work calendar or its changes.
  • The default Calendar cannot be deleted.