As a Project Manager, you may want to measure the resource capacity at any point in order to make informed resourcing decisions for new projects. This view helps you to understand the estimated capacity of his resources in the selected period.
This is calculated asĀ 1- Utilization (Est) as a percentage.
Lets look at an example: Peter's estimated utilization is as follows:
Sept | Oct |
---|---|
17% | - |
So, Peter's capacity for September is [1-(17/100)*100] = 83%. For the remaining months, he is at full capacity, since he has no allocations.