If you need to change the task attributes, you edit a task.
- Go to the Interactive Gantt view for your project.
- Right click on a task and select Edit OR Select a task and click on the edit icon (pencil-shaped).
- The information is divided into 4 tabs : Basic, Advanced, Custom Fields, Details.
- The Basic tab shows attributes like : Name, Start, Finish, Duration, Work, Schedule Type, Constraint Type, Constraint Date, Predecessor, Resources.
- The Advanced tab shows attributes like : % Complete, Priority, State, Start(Actual), Finish(Actual), 'Allow Time Sheets?' checkbox, the financial columns like : Budget, Cost (Est, Material), Cost (Fixed).
- The Custom Fields tab displays all the custom fields attached to a task. You can view/edit values from this tab; per task.
- The Details tab allows you to enter/edit the description text for a task.
For information on tasks attributes, click here
- Certain attributes for summary tasks cannot be edited (start/end dates, duration, schedule type, effort, constraints and financials)
- Summary tasks will always be auto-scheduled.