Resource Load Chart (Real-time)

Resource Load Chart (Real-time)

As projects progress, the project manager might want to get a real-time view of his resources' work loads based on actual approved time. This report provides visibility of free resources & helps the PM adjust allocations to ensure optimal resource utilization. 

This report is a dynamic report that displays the Free hours for resources (resource row) and real-time estimated hours based on actual-approved hours and remaining work at the task and project rows. For past dates, the free hours are based on the actual-approved hours, whereas for present & future dates, the remaining work is computed real-time and spread proportional to the resource's availability.

Lets take an example:

A resource Arnold is assigned to a task 'Project KickOff'

  • Task Schedule: From 11th to 13th in a month i.e 3 days
  • Allocation: 50%
  • Work: 12h (Work)

So, the allocation for Arnold (Hours (Est)) will be divided across the planned dates for the task according to availability and allocation (50%) which is as follows:

11th
12th
13th
444

Arnold fills time-entry of 4 hours for 11th. Today is 12th, 12 PM. This is reflected on 11th (past) for that task row. The remaining effort for the task is now (12 - 4) = 8 hours, which will be spread over today and future duration of the task proportional to Arnold's availability.

As 4 hours of Arnold's working time today has already elapsed (regular working times: 8 AM-5 PM), the remaining available hours for today is 4 and for next day is 8. So, Arnold's remaining availability is  12 h to complete the 8 h of remaining work over the remaining duration of the task. 
Today(at 12:00 PM), Arnold will have to do 2.7 h of work, i.e For 8 hours of remaining work, Arnold is available for 12 hours. So, how much work should he do for 4 hours of availability? (8*4)/12=2.7

And remaining 5.3h (8-2.7) is for 13th.

So, for Arnold, remaining availability (free hours) for the dates is as follows:

11th (past)
12th (present)
13th (future)
4 (8-4 approved hours)2.7 (8-5.3)5.3 (8-2.7)

 

 

If a task is completed before schedule (i.e. %Complete = 100%) then the remaining work (if any) will not be spread over the future duration of the task.

Related content

Resource Load Chart (Real-time)
Resource Load Chart (Real-time)
More like this
Resource Load Chart (Real-time)
Resource Load Chart (Real-time)
More like this
Resource Load Chart
Resource Load Chart
More like this
Resource Load Chart
Resource Load Chart
More like this
Resource Load Chart
Resource Load Chart
More like this
Resource Utilization (Planned v/s Actual)
Resource Utilization (Planned v/s Actual)
More like this