Milestones
A milestone is generally considered to be a key event, typically a deliverable. Milestones often indicate the beginning or ending of major phases or the completion of deliverable(s). Milestones are also excellent reporting points.Â
- You can add a milestone task from the Add option on the Interactive Gantt or by setting the duration of the task as 0d.
- When you assign resources to this task, the allocation will automatically be pre-filled by 0%.
- Â A milestone has 0 duration and as such has no additional calculation effect on the schedule.Â
- A milestone can be linked to other tasks.Â
- You can set constraint dates on a milestone.
- Â These tasks are not shown on the Resource Load Chart.