You can also show relationships between multiple projects by linking tasks across projects. To create an inter-project dependency, you first need the project's System ID  of the predecessor task. This can be found on the Project Details view of that project.
 

  • Go to your project on which you need to create a dependency.
  • Select the Interactive Gantt view from the View drop down, if its not already selected.
  • Select the Columns button from the toolbar and add the Predecessor column to the grid, if not already added to the grid view.
  • Select the task for which you need to add a predecessor.
  • Type the ID of the predecessor task prefixed with the System ID of the predecessor's project in its Predecessor cell. So, the dependency you set in the predecessor column will look like 147497:34. The default dependency type is finish-to-start (FS). You can also indicate alternate dependencies (e.g. FF or SS) to model your project realistically. E.g. 147497:34FF

 

The inter-project dependency links cannot be shown in the Gantt View. 

Related content

Adding inter-project dependencies
Adding inter-project dependencies
More like this
Adding inter-project dependencies
Adding inter-project dependencies
More like this
How to add dependencies
How to add dependencies
More like this
How to add dependencies
How to add dependencies
More like this
Gantt view
Gantt view
More like this
Add Task from Gantt
Add Task from Gantt
More like this