Task Baseline Attributes
Attribute | Description | R/RW |
---|---|---|
%Complete (Planned, Baseline) | It indicates the % Complete (Planned) of the task when it was baselined. This is compared against the Finish (Baseline) date of the project. So, even if your actual Finish date changes, the % Complete (Planned, Baseline) will always be calculated with respect to your Finish (Baseline). | R |
Budget (Baseline) | The budget of the task when the project/task was baselined. | R |
Cost (Est, Baseline) | The estimated cost of the task when the project/task was baselined. | R |
Start (Baseline) | The start date of the task when the project/task was baselined. | R |
Start Variance(Baseline) | The difference in days between the current Start date and the Start date when the project/task was baselined. | R |
Finish(Baseline) | The Finish date of the task when the project/task was baselined. | R |
Finish Variance(Baseline) | The difference in days between the current Finish date and the Finish date when the project/task was baselined. | R |
Work(Baseline) | The Work in hours when the project/task was baselined. | R |
Work Variance(Baseline) | The difference between the current Work and the Work when the project/task was baselined. | R |