Work Calendar Exceptions for Resource
To add Work Calendar Exceptions for User :
- Login with a user with administrator privileges and click on Administration option under the user profile.
- Under the Project Management section, click on Work Calendars.
- Navigate to the Exceptions tab.
- Click Add.
- From the For drop-down, select the user for whom you want to enter an exception.
- In the Summary box, type the details of your event/exception.
- From the Impacts Scheduling drop-down list select an option - Working / Non working.
- From the date picker select a date. You can create the event for a whole day or for a specific time (un-check the All Day checkbox).
- From the Repeat tab, select an appropriate option.
- Click Submit. The exception is added.