Recalculating Projections
Recalculating Projections
As a project progresses, tasks often tend to get delayed. It is very useful for a Manager to be able to compute the finish date based on current progress. Celoxis allows you to compute a projected finish date for your tasks and project. This can be done by clicking on Recalculate Projections for a project.
The attributes which are calculated are:
- Projected Start date of tasks.
- Projected Finish date of a tasks.
- Projected Finish date of a project.
- RAG (schedule and budget) status of project.
To recalculate projections:
- Go to your Project and from menu on right, click on More followed by Recalculate Projections.
, multiple selections available,
Related content
Recalculating Projections
Recalculating Projections
More like this
Recalculating Projections
Recalculating Projections
More like this
Computed attributes of project
Computed attributes of project
More like this
Computed attributes of project
Computed attributes of project
More like this
Project Visual Health Indicators
Project Visual Health Indicators
More like this
Understanding Project Visual Health Indicators
Understanding Project Visual Health Indicators
More like this