Adding inter-project dependencies

You can also show relationships between multiple projects by linking tasks across projects. To set such dependency,  

  • Go to your project on which you need to create a dependency.
  • Select the Gantt
  • Select the task for which you need to add a predecessor and edit it (press e on your keyboard).
  • Navigate to the Predecessors tab.
  • Click on Add. Under the Project drop-down, select the project and then Task who you wish to set as predecessor for this task.
  • Set the Type of dependency and/or the Lead/Lag time.
  • Click on Save.

NOTE: The dependency will NOT be shown under the 'Predecessors' column.


To view dependencies between projects

  1. Create a report of type 'Task' with output type as 'Gantt'. For steps, refer here.
  2. The Gantt part will show you the dependencies as seen in the below screenshot.