Editing a Task
To edit a single task:
- Click on the task you wish to edit from the Views > Tasks menu or any report. In the new slide panel click on Edit.
OR
Go to the Gantt view for your project. Right click on a task and select Edit. Alternatively, you can press the shortcut key 'e' on the task from the Interactive Gantt. - The information is divided into 5 tabs : Basic, Advanced, Custom Fields, Details.
- The Basic tab shows attributes like: Name, Start, Finish, Duration, Predecessor, Resources.
Additionally, there is a checkbox 'Manually Scheduled' which when checked will show up fields like: Work, Schedule Type, Constraint Type, Constraint Date. - The Advanced tab shows attributes like : % Complete, Priority, Start(Actual), Finish(Actual), the 'Allow Time?' checkbox and the financial columns like: Budget, Cost (Est, Material), Cost (Fixed).
- The Predecessors tab is where you can specify dependencies of the task.
- The Custom Fields tab displays all the custom fields attached to a task. You can view/edit values from this tab; per task.
- The Details tab allows you to enter/edit the description text for a task.Â
- The Basic tab shows attributes like: Name, Start, Finish, Duration, Predecessor, Resources.
For information on tasks attributes, click here
- Certain attributes for summary tasks cannot be edited (start/end dates, duration, schedule type, effort, constraints and financials)
- Summary tasks will always be auto-scheduled.
To edit multiple tasks:
You can edit the following attributes of tasks in bulk:
- Schedule Type
- Priority
- Billing Type
- Custom fields attached to Tasks.